Loading...
PUBLIC WORKS COMMITTEE 2026/09/08 Packet PUBLIC WORKS COMMITTEE MEETING TUESDAY, SEPTEMBER 8, 2026 – 5:30 P.M. CITY HALL – UPSTAIRS CITY COUNCIL CONFERENCE ROOM AGENDA I. ROLL CALL/CALL TO ORDER RICHARD WALTHER, CHAIRMAN NANCY NOVIT ALICE LEVERT II. NEW BUSINESS / ACTION ITEMS 1. APPROVAL OF JULY 20, 2026, PUBLIC WORKS COMMITTEE MEETING MINUTES III. INFORMATION ITEMS / NO ACTION 1. LAKE & WOODBINE BRIDGE PROJECT 2. LAKE & SPRUCE BRIDGE PROJECT 3. ROUTE 43 AND WESTLEIGH INTERSECTION IMPROVEMENT PROJECT 4. ROUTE 43 AND EVERETT INTERSECTION IMPROVEMENT PROJECT IV. CIP PROJECT SUMMARY CHART V. PUBLIC COMMENT VI. NEXT MEETING – TBD VII. ADJOURNMENT II. NEW BUSINESS / ACTION ITEM: 1. APPROVAL OF JULY 20, 2026, PUBLIC WORKS COMMITTEE MEETING MINUTES 1 PUBLIC WORKS COMMITTEE MEETING MONDAY, JULY 20, 2026 – 5:30 P.M. CITY HALL – UPSTAIRS CITY COUNCIL CONFERENCE ROOM MINUTES I. ROLL CALL/CALL TO ORDER Chairman Walther called the meeting to order at 5:30 P.M. Aldermen Nancy Novit and Alice Levert were in attendance. Staff attending the meeting included Michael Thomas, Director of Public Works; Corey Wierema, Superintendent of Public Works; Matt Brugioni, Superintendent of Public Works; Ryan Kearney, City Engineer and Jim Lockefeer, Assistant Director of Public Works. II. NEW BUSINESS / ACTION ITEMS 1. APPROVAL OF THE MAY 4, 2026, PUBLIC WORKS COMMITTEE MEETING MINUTES Alderman Novit moved to approve the May 4, 2026, Public Works Committee meeting minutes. Alderman Levert seconded the motion, which carried unanimously. 2. REVIEW AND RECOMMEND APPROVAL TO CITY COUNCIL APPROVAL OF A BID FOR THE FIRE STATION TWO REPLACEMENT GENERATOR PROJECT – COREY WIEREMA Superintendent Wierema reviewed the below presentation slide on the topic. The Committee and City staff discussed the bids received, existing generator site conditions, and restoration efforts. 2 Alderman Levert moved to recommend City Council award of bid to Midwest Power for the Fire Station II Generator Replacement Project in the amount of $74,265, to include a 10% contingency in the amount of $7,427 for a total cost of $81,692. Alderman Novitt seconded the motion, which carried unanimously. 3. REVIEW AND RECOMMEND APPROVAL TO CITY COUNCIL AN ORDINANCE AND RESOLUTION RELATED TO CITY STAFF SWALCO DELEGATES – JIM LOCKEFEER Assistant Director Lockefeer reviewed the below presentation slide on the topic. The Committee and City staff discussed SWALCO costs the City incurs and SWALCO board meeting topics. Alderman Novit moved to recommend City Council approval of the Ordinance that amends the existing Intergovernmental Agreement and a Resolution that both support and identify additional City staff as Alternate SWALCO Directors. Alderman Levert seconded the motion, which carried unanimously. 3 III. CIP PROJECT SUMMARY CHART The Committee and City staff discussed the below presentation slides. 4 5 IV. PUBLIC COMMENT There was no public comment. V. NEXT MEETING – TBD 6 VI. ADJOURNMENT Alderman Levert moved to adjourn the meeting of the Public Works Committee at 6:08 P.M. Alderman Novit seconded the motion, which carried unanimously. Respectfully submitted, Jim Lockefeer Jr. Assistant Director of Public Works III. INFORMATION ITEMS / NO ACTION: 1. LAKE & WOODBINE BRIDGE PROJECT LAKE & WOODBINE BRIDGE PROJECT •Contractor is working on the bridge roadway approaches and railing •Project is anticipated to be completed end of September •Staff coordinating ribbon cutting ceremony with Communications Department III. INFORMATION ITEMS / NO ACTION: 2. LAKE & SPRUCE BRIDGE PROJECT LAKE & SPRUCE BRIDGE PROJECT •Work has been on hold since June due to north embankment water issue •Project update shared at the July 20 City Council meeting; ratification of geotechnical engineering services approved •Staff received the geotechnical report and is currently working with the geotechnical firm and bridge structural engineer to determine the appropriate next steps III. INFORMATION ITEMS / NO ACTION: 3. ROUTE 43 AND WESTLEIGH INTERSECTION IMPROVEMENT PROJECT ROUTE 43 AND WESTLEIGH INTERSECTION IMPROVEMENT PROJECT •Private utility relocations, storm sewer, concrete curb, and road grinding, and pavement base patch work complete •Electrical and landscaping work ongoing, to be completed prior to final paving •Anticipated final completion in October 2026 III. INFORMATION ITEMS / NO ACTION: 4. ROUTE 43 AND EVERETT INTERSECTION IMPROVEMENT PROJECT ROUTE 43 AND EVERETT INTERSECTION IMPROVEMENT PROJECT •Design engineering ongoing with consultant; working to finalize project documents for IDOT bidding •Ongoing coordination with the railroad, outside utilities, and agency permits •Target construction is FY 2029 IV. CIP PROJECT SUMMARY CHART FY ’26 CIP PROJECT SUMMARY CHART FY26 CIP PROJECT SUMMARY CHART – CAPITAL FUND Project Asset Category % Complete Project Timeline Notes Deerpath Streetscape – Construction Streetscape 99%January – October Pending final punch list items. Walden East Bridge Repairs Design Bridge 60%March – September Initial investigation and soil borings have been completed. Final report and recommendations currently being drafted. FY ’27 CIP PROJECT SUMMARY CHART FY27 CIP PROJECT SUMMARY CHART – CAPITAL FUND Project Asset Category % Complete Project Timeline Annual Pavement Resurfacing & Patching Program Road 100%Summer 2026 Crack Sealing Program Road 0%Fall 2026 Concrete Streets Repair Road 100%Summer 2026 Complete. Annual Longline Striping Program Road 100%Summer 2026 Waukegan & Westleigh Intersection Improvements - Construction Road 55%January – October 2026 complete. Storm sewer .Street grinding Electrical and landscaping work ongoing, Concrete Sidewalk/Curb Replacement Road / Sidewalk 100%Summer 2026 Lake & Woodbine Bridge Replacement – Construction Bridge 75%January – September 2026 Lake & Spruce Bridge Rehabilitation – Construction Bridge 40%April – TBD side work on hold. Geotechnical report FY27 CIP PROJECT SUMMARY CHART – CAPITAL FUND Project Asset Category % Complete Project Timeline Notes Rec Center HVAC RTU Replacements Facility 100%August 2026 Project completed – Week of August 24th Senior Center Chiller Replacement Facility 0%TBD Will rebid this project next fiscal year. FS2 Generator Replacement Facility 0%Spring 2027 25-week lead time for generator delivery. South Park Improvements – Design Parks 70%May – October 2026 CC approved 4/6/26. Design continues. Forest Park Beach Steps Repair Study Parks 60%May – October 2026 Preliminary report completed. Staff continuing to work with design firm to finalize report and cost estimates to align for upcoming CIP entry, Townline Park – Safety Netting Installation Parks 0%Fall 2026 Awaiting potential Lowes grant award. Hoping to hear back on the grant late summer / early fall Everett Park – Athletic Field Improvements Parks 0%Fall 2026/Spring 2027 Seeking PWC review 10/5/26; CC review 10/19/26. Awaiting final Storm Sewer Pre-Design: Onwentsia & Poplar Storm Sewer 34%May – October 2026 Design is continuing. Private Fiber Construction Inspection Private Permit 0%April – November 2026 Coordination on project with private fiber company, MetroNet,continues. utility ordinace to better align with the upcoming project. FY27 CIP PROJECT SUMMARY CHART – WATER FUND Project Asset Category % Complete Project Timeline Water Meter Replacement Purchase & Installation Water 35%FY25-FY29 -date. Water Plant Freight Elevator Modernization Water 95%Winter – Fall 2026 Green Bay Watermain Replacement Construction (Linden- Greenwood)Water 100%Summer 2026 Water Distribution System Analysis Water 60%May – October 2026 st . City’s water distribution system model has been and CIP recommendations are being developed. at September 21 City Spruce Lift Station Emergency Generator Replacement Water 0%TBD Valve Repairs Water 75%Summer 2026 Annual Leak Detection Program Water 0%Winter 2026/2027 Annual Valve Turning Program Water 100%Summer 2026 Annual Sanitary Sewer Lining Program Sanitary 0%Fall 2026 V. PUBLIC COMMENT VI. NEXT MEETING: TBD VII. ADJOURNMENT