PUBLIC WORKS COMMITTEE 2024/02/20 Packet
PUBLIC WORKS COMMITTEE MEETING
TUESDAY, FEBRUARY 20, 2024 – 5:30 P.M.
CITY HALL – UPSTAIRS CONFERENCE ROOM
AGENDA
I. ROLL CALL/CALL TO ORDER
ARA GOSHGARIAN, CHAIRMAN
EILEEN LOOBY WEBER
TED NOTZ
II. NEW BUSINESS / ACTION ITEMS
1. APPROVAL OF THE FEBRUARY 5, 2024 PUBLIC WORKS COMMITTEE MEETING
MINUTES
2. REVIEW AND RECOMMEND APPROVAL TO CITY COUNCIL AWARD OF
ENGINEERING DESIGN SERVICES FOR THE WHISPERING OAKS “SAFE ROUTES
TO SCHOOL” SIDEWALK CONNECTIVITY PROJECT – BYRON KUTZ
3. REVIEW AND RECOMMEND APPROVAL TO CITY COUNCIL APPROVAL OF AN
AGREEMENT FOR THE WATER PLANT INTAKE CLEANING – DAN MARTIN
4. DEERPATH COMMUNITY PARK PROJECT UPDATE – CHUCK MYERS
III. FY ’25 CIP PROJECT SUMMARY CHART
IV. PUBLIC COMMENT
V. NEXT MEETING – MARCH 4, 2024
VI. ADJOURNMENT
NEW BUSINESS / ACTION ITEM:
APPROVAL OF THE FEBRUARY 5, 2024
PUBLIC WORKS COMMITTEE MEETING
MINUTES
1
PUBLIC WORKS COMMITTEE MEETING
TUESDAY, FEBRUARY 5, 2024 – 5:00 P.M.
CITY HALL – UPSTAIRS CONFERENCE ROOM
MINUTES
I. ROLL CALL/CALL TO ORDER
Chairman Goshgarian called the meeting to order at 5:05 P.M. Aldermen Eileen
Looby Weber and Ted Notz were in attendance.
Staff attending the meeting included Michael Thomas, Director of Public Works;
Elizabeth Holleb, Director of Finance; Dan Martin, Superintendent of Public Works;
Byron Kutz, Superintendent of Engineering; Chuck Myers, Superintendent of Parks
& Forestry, and Jim Lockefeer, Assistant Director of Public Works.
II. NEW BUSINESS / ACTION ITEMS
1. APPROVAL OF THE NOVEMBER 20, 2023, PUBLIC WORKS COMMITTEE MEETING
MINUTES
Alderman Notz moved to approve the November 20, 2023, Public Works
Committee meeting minutes. Alderman Weber seconded the motion, which
carried unanimously.
2. REVIEW AND RECOMMEND APPROVAL TO CITY COUNCIL AWARD OF BID FOR THE
GROVE CAMPUS ROOF REPLACEMENTS/REPAIR PROJECT
Assistant Director Lockefeer reviewed the below summary presentation slides on
the topic.
2
The Committee and City staff discussed the City’s insurance agency's
deductible and the hail damage experienced throughout southern Lake Forest.
Alderman Weber moved to recommend to City Council award of bid for the
Grove Campus Roof Replacements & Repair Project to Filotto Roofing, Inc. in the
amount of $141,500, to include a 10% contingency in the amount of $14,500, for
a total amount of $156,000. Alderman Notz seconded the motion, which carried
unanimously.
3.REVIEW AND RECOMMEND APPROVAL TO CITY COUNCIL AWARD OF BID FOR THE
ELAWA PARKING LOT RESURFACING CONSTRUCTION PROJECT
Superintendent Kutz reviewed the below summary presentation slides on the
topic.
3
The Committee and City staff discussed project timing, parking lot lighting,
adding a north/south cut through path, construction phasing, landscaping, a
potential Civic Beautification Committee review of the landscape plan, and the
contractor’s experience.
Alderman Notz moved to recommend to City Council award of the low bid for
the Elawa Parking Lot Improvement Project to Maneval Construction and
authorize the City Manager to execute an agreement in the amount of $453,210
as well as approving a 10% contingency in the amount of $40,321 for a total cost
of $493,531. Alderman Weber seconded the motion, which carried unanimously.
III. FY ’25 CIP PROJECT SCHEDULE
The Committee and City staff reviewed and discussed the below presentation
slides.
4
5
The Committee and City staff discussed numerous projects on the above charts
and their current statuses.
IV. PUBLIC COMMENT
There was no Public Comment.
V. NEXT MEETING – FEBRUARY 20, 2024
Director Thomas explained that he will follow up with the Committee via email to
schedule the next meeting.
Alderman Weber expressed some lighting concerns at Illinois Road and Bank
Lane. Staff explained the City’s Street Section would investigate the issue.
VI. ADJOURNMENT
Alderman Weber moved to adjourn the meeting of the Public Works Committee
at 5:59 P.M. Alderman Notz seconded the motion, which carried unanimously.
Respectfully submitted,
Jim Lockefeer Jr.
Assistant Director of Public Works
NEW BUSINESS / ACTION ITEM:
REVIEW AND RECOMMEND APPROVAL
TO CITY COUNCIL AWARD OF
ENGINEERING DESIGN SERVICES FOR THE
WHISPERING OAKS “SAFE ROUTES TO
SCHOOL” SIDEWALK CONNECTIVITY
PROJECT
(presentation slides to be
shared prior to the meeting)
NEW BUSINESS / ACTION ITEM:
REVIEW AND RECOMMEND APPROVAL
TO CITY COUNCIL APPROVAL OF AN
AGREEMENT FOR THE WATER PLANT
INTAKE CLEANING
WATER PLANT INTAKE CLEANING
•FY25 Budget - $215,000
•Process of removing the settled sand and debris from inside the intake pipelines that
extend several thousand feet in Lake Michigan
•Cleaning improves plant operations, increases capacity, and saves operating costs by
reducing backwash cycles
•In 2014, 2018, and 2021 the City has utilized the sole source services of Northern
Divers and their patented cleaning technology
•Allows the WP to stay in operation with minimal shut down times, can be done without
removing the chemical feed system, and no permit is required from the IDNR
•Prior to 2014, the cleaning process was far more labor intensive; required the plant to be
shutdown, pulling all of the debris into the plant’s intake well, and the zebra mussel treatment
lines to be removed and replaced
WATER PLANT INTAKE CLEANING
•Northern Divers has submitted a proposed agreement to complete this project for $215,000
•Staff recommends PW Committee approval to the City Council waiver of the bid process and award of bid to Northern Divers
in the amount of $215,000
NEW BUSINESS / ACTION ITEM:
DEERPATH COMMUNITY PARK
PROJECT UPDATE
FY ’25 CIP PROJECT SUMMARY CHART
CIP PROJECT SUMMARY CHART –CAPITAL FUND
Project Asset Category % Complete Project Timeline Notes
Annual Pavement Resurfacing & Patching Program Road 0%May –August Seeking PWC review on 4/1/24 and CC bid approval on
4/15/24.
Crack Sealing Program Road 0%Fall 2024 Seeking PWC review on 4/15/24 and CC bid approval on
5/6/24.
Concrete Streets Repair Road 0%June –August Seeking PWC review on 5/6/24 and CC bid approval on
5/20/24.
Annual Longline Striping Program Road 0%August –September Seeking PWC review on 6/3/24 and CC approval on
6/17/24.
Waukegan & Everett Intersection (Land Acquisition)Road 5%2024 Applied for STP-Shared grant for land-acquisition with
pending award notification this fall.
Waukegan & Westleigh Intersection (Land Acquisition)Road 15%2024 ROW material provided to both City and School District;
coordination and approval process underway.
Westleigh Resurfacing (41-Western) Phase I Design Road 0%TBD Seeking PWC review on 6/17/24 and CC approval on
7/15/24. Project subject to potential grant award funding.
Deerpath Intersection Traffic Light/Crossing Improvements Road / Sidewalk 0%May –September Seeking PWC review on 4/15/24 and CC bid approval on
5/6/24.
Concrete Sidewalk/Curb Replacement Road / Sidewalk 0%June –August Seeking PWC review on 5/6/24 and CC bid approval on
5/20/24.
Whispering Oaks Sidewalk Connections (SRTS) Design PH 2 Sidewalks 15%Fall 2024
Phase I design approval received, Phase II design to begin
this fall. Seeking PWC review on 2/20/24 and CC bid
approval on 3/4/24.
Gas Light Conversion Program Parkway 0%Sprig –Fall 2024 conversion plan and map to be developed.
McClory Bike Path Resurfacing (Ryan to Illinois)Path 0%Summer 2024 Seeking PWC review on 4/15/24 and CC bid approval on
5/6/24.
CIP PROJECT SUMMARY CHART –CAPITAL FUND
Project Asset Category % Complete Project Timeline Notes
Deerpath Streetscape –Design PH 2 Streetscape 50%Summer / Fall 2024
Phase II design progressing. Seeking change order approval
at 2/5/24 CC meeting for additional design services.
Construction anticipated to begin Spring 2025.
CBD Infrastructure Improvements –Design Streetscape 0%June –September
Seeking PWC review on 5/20/24 and CC approval on
6/3/24. Subject to project scope being defined in Spring
2024.
McLennon-Reed Bridge Repairs –Design Bridge 90%Winter 2024 Design progressing.
McLennon-Reed Bridge Repairs –Construction Bridge 0%January 2025 –June 2025
Staff intends to align construction with Lake-Woodbine
Bridge Project to minimize overall construction impacts to
Lake Road residents.
Lake-Woodbine Bridge Reconstruction –Design PH 2 Bridge 35%Summer 2024 Phase II design underway and progressing.
Lake-Woodbine Bridge Reconstruction –Construction Bridge 0%December 2024 –September 2025 Working towards bidding with State’s bid process for
August 2024.
2024 Bridge Inspections Bridge 0%May Seeking PWC review on 3/4/24 and CC bid approval on
3/18/24
Ringwood Bridge Replacement Phase I Design Bridge 0%2024 –2025 Seeking PWC review on 4/1/24 and CC bid approval on
4/15/24.
Elawa Parking Lot Resurfacing and Expansion –Construction Parking Lot 0%April –May Construction to occur in April & May of 2024.
ADA Transition Plan Facilities / Right of Way /
Parks 50%April Facility visits completed. First draft of plan in completed.
Staff review underway.
CIP PROJECT SUMMARY CHART –CAPITAL FUND
Project Asset Category % Complete Project Timeline Notes
Gorton Community Center Patio & Drop in Center Facility 5%May –August Staff presented project to HPC; project needs to return to HPC.
Public Safety Water Cooled Chiller Replacement Facility 10%Winter / Spring 2024 Project coordination underway. Project to begin and be
completed during the winter/spring months of 2024.
North Beach Building & Pavilion Roof Replacement Facility 5%September –October 2024 Seeking PWC bid review on 3/4/24 and CC bid approval on
3/18/24. Construction to occur after Labor Day.
Grove Campus Roof Replacements Facility 10%March –April 2024 Seeking PWC bid review on 2/5/24 and CC bid approval on
2/20/24.
Rec Center HVAC Replacements (RTUs)Facility 0%June –July 2024 Seeking PWC review on 6/3/24 and CC approval on 6/17/24.
Forest Park Bluff Slope Stabilization Forest Park / Beach 50%September 5, 2023 –
March 2024
Construction began 9/5/23. Estimated construction completion in
December or January.
Forest Park Boardwalk Forest Park / Beach March –May 2024
Boardwalk Project: Received construction bids and fundraising
efforts for the needed $750,000 continues via Park and
Recreation Foundation. Staff will seek City Council approval to
proceed with construction at their 12/4/23 meeting.
Construction is estimated to begin mid-winter and be completed
by memorial day.
Sailboat Compound Expansion Forest Park / Beach 0%Spring 2024 Seeking PWC bid review on 2/5/24 and CC bid approval on
2/20/24.
Beach Restoration (Sand Replenishment)Forest Park / Beach 0%September –
November 2024 Seeking PWC review on 7/15/24 and CC approval on 8/5/24.
CIP PROJECT SUMMARY CHART –CAPITAL FUND
Project Asset Category % Complete Project Timeline Notes
Tennis Surface Maintenance (Northcroft/Waveland/Everett)Parks 0%Spring 2024 Seeking PWC bid review on 2/5/24 and CC bid approval on
2/20/24.
West Park: Tennis Court Design Parks 0%May –September Seeking PWC review on 4/15/24 and CC bid approval on 5/6/24.
West Park: Tennis Court Construction Parks 0%TBD Seeking PWC review on 8/5/24 and CC approval on 9/3/24.
Northcroft Park: Handball Courts Installation Parks 0%Fall 2024 Seeking PWC review on 6/17/24 and CC approval on 7/15/24
Cemetery Ravine Restoration –Design Ravine 0%May –September Seeking PWC review on 3/18/24 and CC bid approval on 4/1/24.
Walden Ravine Bed Restoration –Design Ravine 0%May –September Seeking PWC review on 3/18/24 and CC bid approval on 4/1/24.
Seminary Ravine Improvements Construction Ravine 0%TBD Seeking PWC review on 4/15/24 and CC bid approval on 5/6/24
(subject to Federal grant award approval timing).
Annual Storm Sewer Lining Program Storm Sewer 0%Fall 2024 Seeking PWC review on 3/18/24 and CC bid approval on 4/1/24.
Ahwahnee Road Storm Sewer Upgrade Design Storm Sewer 85%Fall 2024 Design progressing.
Ahwahnee Road Storm Sewer Upgrade Construction Storm Sewer 0%December 2024 –Spring
2025
Pending possible grant announcement from SMC this Spring
2024.
Scott-Wisconsin and Griffith-Woodland Storm Sewer
Improvement Design Storm Sewer 0%May –September Seeking PWC review on 4/1/24 and CC bid approval on 4/15/24.
Stormwater Management Study Update Storm Sewer 0%May –September Seeking PWC review on 4/15/24 and CC bid approval on 5/6/24.
CIP PROJECT SUMMARY CHART –WATER FUND
Project Asset Category % Complete Project Timeline Notes
Membrane Module Replacement Water 0%Fall 2024 Seeking PWC review on 6/17/24 and CC approval on 7/15/24.
Water Meter Replacement Project Design Water 60%Summer 2024
Vendor demos completed. Technical Report completed. Project
will bid out this winter for three-year installation/implantation
pricing.
Water Meter Replacement Purchase & Installation Water 0%TBD Seeking PWC review on 7/15/24 and CC approval on 8/5/24.
Pump VFD Upgrade (2 Year)Water 50%May First year contract completed; second year VFDs to be
completed by May 2024.
Water Plant Intake Cleaning Water 0%Early Summer 2024 Seeking PWC review on 2/20/24 and CC bid approval on 3/4/24.
Watermain Replacements (Field/Spring/Mayflower) & Valve Repairs Water 0%Summer –Fall 2024 Seeking PWC review on 4/1/24 and CC bid approval on 4/15/24.
Elevated Tank Painting –Design Water 0%June –September Seeking PWC review on 5/6/24 and CC bid approval on 5/20/24.
Annual Sanitary Sewer Lining Program Sanitary 0%Fall 2024 Seeking PWC review on 3/18/24 and CC bid approval on 4/1/24.
Dye Testing Sanitary 0%Spring –Summer 2024 Seeking CC approval on 2/5/24.
Manhole Lining and I&I Repairs Sanitary 0%Summer –Fall 2024 Seeking PWC review on 5/6/24 and CC bid approval on 5/20/24.