PUBLIC WORKS COMMITTEE 2014/07/08 MinutesPUBLIC WORKS COMMITTEE
TUESDAY, JULY 8, 2014 – 4:30 P.M.
MUNICIPAL SERVICES – 800 N. FIELD DRIVE
TRAINING ROOM
MEETING MINUTES
I. CALL TO ORDER/ROLL CALL: Chairman Waldeck called the meeting to order at
4:35 p.m. Aldermen Tack and Moreno were present.
City staff in attendance included Michael Thomas, Director of Public Works;
Robert Ells, Superintendent of Engineering; Dan Martin, Superintendent of Public
Works; Donna Dunn, Assistant to the Director of Public Works; Robert Kiely, City
Manager; John Gulledge, Chief Water Plant Operator; and Cathy Czerniak,
Director of Community Development.
Other attendees included presenter Brian Hackman from Strand Associates and
member of the public John Looby.
II. APPROVAL OF THE APRIL 14, 2014 PUBLIC WORKS COMMITTEE MEETING MINUTES:
Alderman Moreno moved to approve the minutes of the April 14, 2014 meeting
as written. Alderman Tack seconded the motion, which carried unanimously.
III. UPDATE ON WATER PLANT STUDY:
a. Review of Water Plant Project History
Director of Public Works Michael Thomas reviewed the Water Plant
rehabilitation project timeline, which began in 1995 and included a
thorough study and review of the Water Plant, installation of a transmission
main and revetment, and the water plant project itself. The timeline
included all of the milestones for the review process, approvals, and
construction.
b. Review of Refined Scope of Services
Director Thomas introduced Brian Hackman of Strand Associates who
reviewed the refined Scope of Services with the Public Works Committee.
Mr. Hackman addressed the concerns of the Aldermen at the last Council
meeting via the revised Scope of Services. The revised Scope included a
review of the existing conditions and water system demands,
recommended short-term and long-term improvements to the membrane
system, an analysis of the preliminary needs of the existing systems, the
development of the Water Treatment Plant Master Plan, and supplier
communication and meetings.
Public Works Committee
Meeting Minutes from July 8, 2014
Page 2 of 9
Alderman Moreno asked about the interchangeability of parts and
equipment from different manufacturers. Mr. Hackman explained that
the parts can be interchangeable, but that is something they plan to
review as part of the proposed study. Alderman Moreno explained that
understanding the critical path and interchangeability is incredibly
important in terms of this study. She is concerned about utilizing a sole
source for critical components, while using a sole source for smaller
components or less critical components is not as much of a concern. In
her opinion, the modules are a critical component and now that the
modules are no longer being manufactured, the need to retrofit the Plant
has created a substantial expense in order to reestablish the critical path.
Finding a way to prevent this from happening again in the future is a
priority.
As Mr. Hackman reviewed the Scope of Services, Alderman Moreno
asked for clarification on items 3.b. and 3.h. Mr. Hackman explained the
clearwell storage and the intent of item 3.b. He then explained that
“demolition and abandonment of existing facilities” in item 3.h. was in
regards to old facilities still housed within the Plant after the rehabilitation
project. It was not referring to demolition or abandonment of any of the
current Plant facilities. The Committee recommended that specific item
be clarified in the Scope of Services to make that clear. Mr. Hackman
agreed to revise item 3.h. to reflect this.
Chairman Waldeck asked if there is a prioritized list of what is important to
Council as it relates to this study. Alderman Moreno noted that these
priorities should include flexibility, reasonable cost, safety, quality, and
availability. City Manager Robert Kiely explained that Mr. Hackman has
clear direction, based on the last Council discussion, to provide a
comprehensive list of variables that should be used to determine the best
membrane supplier for The City of Lake Forest. Once the City has the
preliminary data and findings, it will be appropriate for City Council to
have another discussion at that time.
No motion was required for this item.
c. Review of Study Progress
Mr. Hackman reviewed the schedule of tasks to be completed as part of
the study. To date, they have established projections based off of City-
provided data and discussed future demands based on population
projections. None of the projections to date show the need for the Plant
to be any larger than 14 MGD until 2020 – 2023. Until then, the 14 MGD
Plant would be sufficient to meet the current demand, unless City Council
believes the plant should be increased in size to address future irrigation
demands.
Public Works Committee
Meeting Minutes from July 8, 2014
Page 3 of 9
Mr. Hackman then reviewed a summary of membrane system items with
the Committee. Alderman Tack asked if narrowing the vendor list to those
that meet the current quality standards reduce the list. Mr. Hackman
replied that the current quality standards could be a good disqualifier.
After reviewing a statement in the letter the City received from
AquaSource, the Committee agreed that clarification is necessary to
determine if the company will bear any of the burden of the cost to
change out these modules. Chairman Waldeck and Alderman Moreno
also recommended staff review the contract to determine if AquaSource
has any contractual responsibility to resolve this issue.
Mr. John Looby commented that the Plant should be updated to
something that won’t continually be a problem for the City.
d. Approval of Purchase for 24 Additional Modules
At the end of May, Director Thomas requested that AquaSource produce
an additional 24 modules to provide the City with more time to make
necessary changes to the Plant. Staff received confirmation this morning
that AquaSource will make 24 modules at the same price as the most
recent order received in May 2014. These additional modules will be
stored at the Plant until they are placed into service in May 2015. With this
purchase, the Plant will not have to replace modules for five years. Staff is
requesting the approval to purchase the additional modules. Director
Thomas explained that this purchase is not budgeted for FY2015 and
would therefore reduce available dollars for FY2016’s Water Fund Capital
projects. Therefore, staff recommends approval to advance the
purchase by one fiscal year.
Alderman Tack moved to approve the purchase of the additional 24
modules in the amount of $201,770. Alderman Moreno seconded the
purchase, which carried unanimously.
e. Approval of Design for Algae Pre-Screen System
Director Thomas reviewed the two major issues that limit pumpage at the
Plant, which are cold water and algae. Staff is requesting approval of a
contract to design an algae pre-screen system; the design would be
completed by December 2014. Once the design is complete, staff will
place the project out for bid and bring it to City Council for approval. This
will allow for construction to occur during the winter and spring months
and be completed before the heavy water demands next summer.
Director Thomas estimates the construction of the pre-screen system will
cost approximately $600,000. The design for the project is budgeted in
FY2015, but similar to the purchase of additional modules, the cost of the
Public Works Committee
Meeting Minutes from July 8, 2014
Page 4 of 9
construction will reduce available dollars from the Water Fund Capital
amount in FY2016.
The Committee confirmed that the pre-screen system will work with any
type of module and that the algae issue is something that needs to be
remedied regardless of the module. The Committee asked if the pre-
screen system will change the flavor of the water. Director Thomas
explained that this system should remove any “musty” type odor from the
water that some users may have experienced when algae was an issue in
the past.
Alderman Tack moved to approve the contract to design the algae pre-
screen system. Alderman Moreno seconded the motion, which carried
unanimously.
IV. STORM WATER MEETING FOR 4TH WARD: City Manager Kiely noted that the
proposed storm water meeting is not just for residents in the 4th Ward. He
explained that staff is developing a storm water policy so there is consistency in
how residents requests are handled by staff and City Council members. The
current system in Lake Forest is designed for 10-year storms which is simply a rate
of the rainfall, not that a severe storm occurs once every 10 years. Storm water
will continue to be an issue in the community and the City needs to have an
official policy in place that is approved by City Council. Once there is a policy,
staff can have better conversations with homeowners. Management of storm
water is not a City problem alone.
In the upcoming months, staff will have a proposed program to present to the
Committee. Staff will need clear direction from the City Council in order to move
forward. Committee members commented that keeping water out of homes is
the priority, and second to that is flooding in the roadway that closes the street.
Staff asked if not having water in yards is an expectation that Council shares; the
Committee agreed that storm water in private yards, although somewhat of a
concern, does not trump water in basements or roadways. The Committee
discussed to what extent City Council should be using public funds to correct a
private problem. The Committee also discussed that storm water is part of an
integrated system. Storm drains are one piece of it and if the water is excessive
and the drains can’t handle it, it becomes a larger problem. Committee
members agreed that there needs to be more information and education about
storm water and drainage. Staff and residents needs to work together to solve it
collectively.
Mr. John Looby commented that overland flooding causes his home to flood. In
one of the most recent storms, there was 6” of water against his house, which
because he has no basement, spilled into his first floor. At the time of the rain,
Public Works Committee
Meeting Minutes from July 8, 2014
Page 5 of 9
there was 14” of water or more in his yard. He has never had this much water
before. Mr. Looby doesn’t understand what is different today than over the last
30 years, but he firmly believes that something has to be done to resolve this
issue. City Manager Kiely responded that staff needs to analyze what is really
causing the problem. This would be part of the proposed program so that the
issue can be addressed accordingly. Superintendent of Engineering Bob Ells
added that storm sewer upgrades only help when the water gets to the streets.
It will not resolve all of the overland/yard flooding issues. Additionally, there has
been a substantial amount of rain which has caused the ground to be saturated.
Large, heavy rains on saturated soils can cause significant yard flooding as has
been the case many times this past spring and summer. Alderman Moreno
commented that in terms of development, more attention needs to be paid to
make sure that water is being diverted to one of the appropriate water
detention areas.
Staff will set up meetings with the two neighborhood groups that have been
most affected by storm water during recent storms and will work on a program
that will be presented to the Public Works Committee in upcoming months.
V. FY2015 ENGINEERING CIP UPDATE:
a. Annual Resurfacing Project
Superintendent Ells reported that this project is 80% complete. The final lift
of asphalt for Atteridge Road, McKinley Road, and Conway Farms Drive
will occur next week. Landscape restoration and striping will follow, with a
majority of the work to be complete by mid-August.
b. Patching & Pothole Program
The original contract for large patches in the amount of $453,000 has
been completed. The contract was amended to include $50,000 in small
patch/pothole repairs, which is scheduled to begin in late July. Any
remaining areas in need of patching/repair will be repaired by the City’s
Streets Section.
c. Concrete Street Project
This project is scheduled to start this week and will be completed in
approximately 45 days.
d. Concrete Curb & Sidewalk Replacement Project
The concrete curb and sidewalk replacement will begin this week and
take approximately 45 days to complete. There are areas scattered all
over Lake Forest that are scheduled for replacement as part of this
project.
Public Works Committee
Meeting Minutes from July 8, 2014
Page 6 of 9
e. Oak Knoll Water Main Project
The Oak Knoll Water Main Project is underway. The new 8” water main
has been installed and crews are now working on the tie-ins across the
road, valves, and fire hydrants. Work is scheduled to be complete by mid-
September, but it will most likely be finished before then.
Chairman Waldeck asked if there is a program in place to address shoulders that
have washed out in areas with no curbs. The intensity of recent storms has
created substantial drop-offs from the stone/gravel being washed out.
Superintendent of Public Works Dan Martin replied that the Streets Section will
build these washed out areas back up.
Alderman Moreno asked if boulders are encouraged for areas without curb and
gutter. Director Thomas explained that there is a permitting and review process
for residents that wish to install boulders. The Committee discussed the
enforcement of illegally placed boulders and the priority of this enforcement
among other responsibilities. Chairman Waldeck stated that she has received a
number of complaints over the years and asked if a form letter could be sent out
to people in violation. Being that there is an Ordinance, staff has a mechanism
available to issue tickets or citations. City Manager Kiely explained that staff has
done this in the past, but received substantial pushback from the community
and it was tabled. If this is something Council feels is a priority to address, they
have to be prepared for the public outcry. Director of Community Development
Cathy Czerniak added that if there are specific complaints, the Code
Enforcement Officer can investigate and follow up on those complaints. The
Committee agreed to handle complaints in this manner until the issue of
boulders is discussed at a later time.
VI. DISTRICT #67 AND #115 REFUSE & RECYCLING COLLECTION: Director Thomas
reported that effective July 1, 2014, the City is providing refuse and recycling
services to all District 67 schools and West Campus. The City is unable to provide
service to East Campus because they use a compactor, which would have
been a substantial capital cost to the City. The City entered into an
Intergovernmental Agreement with both districts for a term of three years.
VII. WATER WELL STUDY UPDATE FOR 5+ ACRE PARCELS: As part of the water rate study
last fiscal year, staff was instructed to investigate the possibility of allowing
residents or property owners with parcels greater than five acres to install a well
for irrigation. Assistant to the Director of Public Works Donna Dunn reviewed a
map of the eligible 5+ acre properties in Lake Forest. She explained that there
are 12 institutional parcels, 33 commercial parcels, and 70 residential parcels
including homeowner’s associations and common areas that are eligible based
on the proposed minimum lot size of five acres. City properties (except for the
Public Works Committee
Meeting Minutes from July 8, 2014
Page 7 of 9
Deerpath Golf Course), Lake Forest Open Lands, Forest Preserve District, Metra,
ComEd, and Fort Sheridan properties were removed from the list.
The next step will be to research the impact on water revenue and Plant
demand should these properties install a well for irrigation purposes in the future.
Chairman Waldeck suggested, based on a comment from Alderman Moore,
that other factors also be considered when determining if a property is eligible
for a well. There may be properties under five acres that would benefit from the
installation of an irrigation well that under the current proposal would not be
considered.
VIII. EAST SIDE TRAIN STATION PROJECT UPDATE:
a. Painting & Tuck Pointing
Superintendent Ells reported that the plans and specifications for the
painting and tuckpointing at the East Side Train Station have been
approved by IDOT District 1. Harboe Architects will be working with
Gewalt Hamilton on the Phase III submission for IDOT. The Committee
discussed the schedule for painting and tuckpointing given that the Bike
Path Project may be postponed until 2015. Staff was making a push to
have the painting and tuckpointing completed in 2014, but the IDOT bid
process will most likely be completed until mid-September. Once the
project is bid, decisions will need to be made as to how the project is to
proceed. IDOT has to review and approve bids from the bid opening
before they can go to City Council for approval. Staff believes that the
tuckpointing and bike path construction can occur at the same time.
Because of the dirt these two projects will create, staff recommends that
the painting part of this project occur AFTER the bike path and tuck
pointing are complete. This would therefore have the painting of the
station buildings to begin in mid-summer next year.
b. McClory Bike Path from Woodland Road to Illinois Road
Superintendent Ells reported earlier that the Bike Path Project may be
postponed until 2015 depending on decision regarding the ComEd
proposal to bury the electrical lines on McKinley from Deerpath to
Westminster.
c. ComEd Line Bury – July 21, 2014 City Council
The City received a letter from ComEd indicating that they would need
time to engineer and design the placement of ducts to pull cable and
wire through in order to bury the lines on McKinley at a cost of $617,000.
Staff contacted the company that performed work at Forest Park to verify
what ComEd submitted, which must be reviewed before the design for
the Bike Path can be done. A representative from ComEd will present at
Public Works Committee
Meeting Minutes from July 8, 2014
Page 8 of 9
the July 21, 2014 City Council meeting. Superintendent Ells noted that the
City has to be cautious of the schedule because ComEd is ready to
proceed with the pole relocation and if the City decides to wait too long,
ComEd won’t be able to perform the relocation this summer or early fall.
The Committee asked if the City can hire a contractor to bury the ComEd
lines. Superintendent Ells explained that the City cannot. The conduit is in
place, and the cost provided by ComEd may include new conduit so
there is a chance the amount could change.
IX. UPDATE ON SPRINKLING BAN:
a. Number of Complaints
Superintendent Martin reported that staff has received one complaint for
a property in violation of the sprinkling restrictions.
b. Warning Notice: Violation of Irrigation Restrictions
Superintendent Martin reviewed the notice that was sent to the one
property in violation. Staff will maintain a database of compliance issues,
and will work with the Code Enforcement Officer in Community
Development if citations or administrative hearings are required. The
Committee asked if sprinkler companies were notified of the change.
Superintendent Martin stated that they were also notified with the same
postcard sent to residents.
X. WATER METER CHANGE OUT DISCUSSION: Director Czerniak explained that there
was a recent request to downsize a resident’s water meter due to the recent
rate changes. Before this change would be allowed, the resident would be
required to complete a calculation sheet of the number of fixtures, if an irrigation
system is present, etc. for a planner to review and determine a sufficiently sized
meter. For this specific request, the calculation sheet showed that a 1 ½” meter
is sufficient for the property.
In the past, residents have typically wanted to upgrade, not downsize. The
process for this has been to take the smaller meter back and the resident pays
for the cost of a new, larger meter. This is staff’s first request to downsize a meter,
which would result in a credit. Staff is asking for direction in case this becomes
more common. The Committee asked who installs the meter. Director Czerniak
stated that Water & Sewer Utilities employees remove the old meter and install
the new meter. The Committee agreed that no credits will be issued for
downsizing a meter and that the same process will apply regardless of whether
meters are being upgraded or downsized. Should the request become more
common, the Committee will readdress it.
XI. OPPORTUNITY FOR PUBLIC COMMENT: None.
Public Works Committee
Meeting Minutes from July 8, 2014
Page 9 of 9
XII. NEXT MEETING: Director Thomas will confirm a date and time for the Committee’s
next meeting in September.
XIII. ADJOURNMENT: Alderman Tack moved to adjourn the meeting of the Public
Works Committee at 6:30 p.m. Chairman Waldeck seconded the motion, which
carried unanimously.
Respectfully submitted,
Donna Dunn
Assistant to the Director of Public Works