PUBLIC WORKS COMMITTEE 2020/02/19 Packet
PUBLIC WORKS COMMITTEE MEETING
WEDNESDAY, FEBRUARY 19, 2020 – 6:30 P.M.
MUNICIPAL SERVICES TRAINING ROOM
AGENDA
ROLL CALL/CALL TO ORDER
Raymond Buschmann, Chairman
Michelle Moreno
Melanie Rummel
INFORMATION ITEMS
I. UPDATE ON THE BURR OAK STORM SEWER DESIGN – MICHAEL THOMAS
DISCUSSION ITEMS
I. PROJECT CONTINGENCY & CHANGE ORDER APPROVAL AUTHORITY – ELIZABETH
HOLLEB & MICHAEL THOMAS
ACTION ITEMS
I. APPROVAL OF THE DECEMBER 10, 2019 PUBLIC WORKS COMMITTEE MEETING
MINUTES
II. REVIEW AND RECOMMEND APPROVAL TO CITY COUNCIL THE WATER PLANT
GENERATOR RADIATOR REPAIR BID – DAN MARTIN
III. REVIEW AND RECOMMEND APPROVAL TO CITY COUNCIL FIRE DEPARTMENT’S
LOCKER ROOM PROJECT BID – DAN MARTIN
PUBLIC COMMENT
NEXT MEETING – MARCH 19, 2020
ADJOURNMENT
INFORMATION ITEM:
UPDATE ON THE BURR OAK
STORM SEWER DESIGN
(INFORMATION TO BE
PRESENTED AT MEETING)
DISCUSSION ITEM:
PROJECT CONTINGENCY &
CHANGE ORDER APPROVAL
AUTHORITY
CONTINGENCY FUNDS
AND
CHANGE ORDERS
Public Works Committee –Wednesday, February 19
Outline
•Background
•Current Practices –Contingency
•Current Practice -Change Orders
•Recommendations
•Questions
Background
February 20, 2019 –PW Committee Contingency Discussion
•NBAR Project Contingency Discussion
•No contingency vs. 10% contingency
•Contingency Policy Discussion
October 7, 2019 –Purchasing Directive Revisions Committee Established
•Committee comprised of City staff
•Charged with reviewing & revising all sections of purchasing policy
•PW directed to review contingency & change orders
Current Practices –Contingency
•No direct contingency policy outlined in current Purchasing Directive
•Staff generally applies a 10% contingency to total project budgets
•Utilized for projects that may have a certain degree of risk/uncertainty
•Underground projects
•Building & facility projects
•May request a greater/smaller contingency (5% -15%)
•Bids received
•Contractor experience
•If contingency is not utilized, PW staff often recommends using savings for other CIP projects
Current Practice -Change Orders
•Defined policy outlined in current Purchasing Directive (included in packet)
•Change orders < $20,000, above and beyond any approved contingency funds are approved by City Manager
•Justification and detail is provided to City Manager via City’s ERP system
•Change orders > $20,000, above and beyond any approved contingency funds are approved by City Council
Recommendations
•Staff recommends that current contingency & change order practices be defined within the Purchasing Policy
•Discussion…
•Contingency
•Require a minimum 10% contingency
•Change orders
•Staff to work with Purchasing Directive Revisions Committee to incorporate updated language
•All Purchasing Directive revisions to be recommended for approval by the Finance Committee
•April 20, 2020 meeting
Questions?
Administrative Directive 3-5
Purchasing Procedures
Page 6
5.8 Local Sources and Preference.
A. Local Sources. The City Manager shall endeavor to include vendors located
within the City for procurements subject to this Directive where practical.
B. Local Preference. The City Manager is authorized to accept the bid or quote of
a Local Vendor where the quality, customer service, responsiveness, and other
aspects of the Local Vendor and its bid or quote are at least equivalent to the
lowest vendor and its bid or quote.
5.9 Online Purchases: Online purchases must be from reputable sources, reducing the
risk to the City. All personal and credit card information transmitted through the
internet must be protected with a current, secure encryption protocol that protects
data as it travels over the Internet. Care should be taken with City information to
prevent fraudulent charges. If the option is provided, do not store any payment
information (e.g., credit card numbers) on any website. Approval processes and
procedures must be followed as outlined in section 4.0, ensuring the best possible
price.
5.10 Change Orders and Contract Modifications.
A. Department Head's Authority: Other Than Construction. In procurements other
than for construction, the Department Head responsible for supervision of any
contract shall have authority to authorize any change to such contract that, when
added to all other changes to such contract, would not increase the original
contract price by more than 10% or $2,000, whichever amount is less. If the
change order plus the original contract is $20,000 or more, the contract will
require City Council approval.
B. Department Head's Authority: Construction. In procurements for construction,
the Department Head shall have the authority to authorize any change to a
contract for construction that would not increase the original contract price
approved by the City Council.
C. City Manager's Authority. The City Manager shall have authority to authorize
any change to a contract that, when added to all other changes to the contract,
would not increase the contract price as authorized by the City Council by more
than 5% or $20,000, whichever amount is less.
D. City Council's Authority. The City Council shall have authority to authorize all
other changes to contracts.
E. Necessary Finding. Any change to a contract that, when added to all other
changes to the contract, increases or decreases (a) the original cost of the
contract by $10,000 or more, or (b) the time of completion of the contract by
30 days or more, shall not be approved without a written determination by the
City Manager and the Department Head that:
Administrative Directive 3-5
Purchasing Procedures
Page 7
(i) the circumstances said to necessitate the change were not reasonably
foreseeable at the time the contract was signed; or
(ii) the change is germane to original contract as signed; or
(iii) the change is in the best interest of the City.
Each such change order and each such written determination shall be in the
form of the Change Order Approval Form in Attachment C to this Directive and
shall be preserved in the contract's file. 720 ILCS 5/33E-9.
F. Re-Bid Required. Any change order to a City contract that, when added to all
other changes to the contact, increases the original price of the contract or any
subcontract by 50% or more, shall require the portion covered by the change
order to be resubmitted to bidding or quotes in the same manner as applicable
to the original contract or subcontract. 50 ILCS 525/1 et seq.
G. Emergencies. All emergency change orders must be presented to the City
Manager as soon as practical, and those requiring City Council approval must
be submitted to the City Council for ratification at the next scheduled Council
meeting.
5.11 Procurements Funded by "Donated" Funds. Any procurement of construction,
repair and maintenance projects, supplies and services to be funded by monies
donated to the City by third parties shall be governed by the terms of this Directive.
This limitation does not apply to public improvements constructed pursuant to an
annexation, subdivision or development agreement.
5.12 Information Technology and Computer Procurements. All new procurements in
the area of information technology, e.g. hardware, software, hosted services
(Cloud), etc. are subject to a needs assessment and provision of information for
review prior to commencing the procurement process. The Technology Pre-
purchase Needs Assessment, in the form of Attachment D, must be approved by
the City Manager for each proposed procurement.
5.13 City's Reservation of Rights. The City shall have the authority to reject the low
bid, to accept any item of a quote or bid, to reject any and all quotes or bids, to
accept and incorporate corrections or clarifications following bid opening and to
waive irregularities and informalities in any quote or bid submitted or in the bidding
process, when to do so would not, in the City's opinion, prejudice the bidding
process or create any improper advantage to any bidder.
5.14 Third-Party Payee. The City Manager or other person designated by this Directive
shall seek to limit procurements involving a Third-Party Payee. All procurements
involving a Third-Party Payee shall be subject to City Council approval if the
payment to the Third-Party Payee is reasonably expected to exceed $20,000 over
the life of the contract or engagement. The only exceptions to this are limited to:
1) construction contracts in which the City Council has approved a contract with a
How are project contingencies handled for major projects? Does governing board authorize
the contingency amount or is that outlined in your purchasing procedures?
Arlington Heights: Governing Board approves contingency
Buffalo Grove: Project contingencies are made part of the total contract award. The Board is
made aware that Village Staff will hold and control the contingency funds.
Crystal Lake: In many cases, a contingency allowance is provided as part of City Council
approved contracts. Often times, this contingency allowance is 10%. Any use of this
contingency must be approved by the City Manager prior to authorizing the use of the
contingency. A Contract Amendment and Change Order Approval Form must be completed and
routed to the Procurement Officer.
Deerfield: Board authorizes total contract amount.
Glenview: Staff request approval of a contingency amount with the board approval of the
project.
Highland Park: Approved by Council as part of the project. Must also be included in the requisition.
Libertyville: Village practice is to include contingency authorizations in resolutions approving
the initial purchase.
Lincolnshire: Pay approval follows the purchasing policy, same as a new purchase. Policy
provided in purchasing procedures.
North Aurora: Not clear in our policies.
Northbrook: Resolutions usually allow Manager to approve contingencies up to 10%. Anything
higher needs supplemental resolution.
Northfield: We always include a contingency in the amount the Board approves.
Waukegan: This falls under our change order language:
Sec. 2-462. - Change orders.
(a) In the event a contract necessitates any increase in the original contract price of 5% of
the City Council approved annual amount, but not to exceed $5,000, the Mayor or their
designee may grant approval of the change order.
(b) Contract increase changes in the aggregate of 5% of the approved annual contract
amount, and / or in excess of $5,000, must be resubmitted to the city council for
authorization before a change order may be issued.
(c) The Mayor or their designee may determine that a change order which significantly
changes the nature, value, or scope of the contract requires resubmission to the bidding
process under the provisions of section 2-458.
ACTION ITEM:
APPROVAL OF THE DECEMBER 10,
2019 PUBLIC WORKS COMMITTEE
MEETING MINUTES
1
PUBLIC WORKS COMMITTEE MEETING
TUESDAY, DECEMBER 10 2019 – 6:30 P.M.
MUNICIPAL SERVICES TRAINING ROOM
MINUTES
ROLL CALL/CALL TO ORDER
Chairman Raymond Buschmann called the meeting to order at 6:30 P.M.
Aldermen Michelle Moreno and Melanie Rummel were present.
Staff in attendance included Michael Thomas, Director of Public Works; Dan
Martin, Superintendent of Public Works; Bob Ells, Superintendent of Engineering;
Jason Wicha, City Manager; Mike Strong, Assistant to the City Manager; Cathy
Czerniak, Director of Community Development and Jim Lockefeer, Management
Analyst.
Also in attendance were six Lake Forest residents living in the Oxford Road area.
INFORMATION ITEMS
I. OXFORD ROAD STORM SEWER SSA – MIKE STRONG & MICHAEL THOMAS
Director Thomas provided some background information on the topic. He
explained that after some property owners in Oxford had learned about the
City’s upcoming Burr Oak Storm Sewer Project they inquired if they would be
able to initiate their own storm sewer project on Oxford. He explained that the
property owners were informed by City staff that there is an opportunity,
however, the cost of their project would be the responsibility of the property
owners on Oxford. He explained that these homeowners were informed of the
City’s ability to provide project assistance through the establishment of a Special
Service Area (“SSA”). He explained that he and Mike Strong began to develop
materials for the potential SSA that included project timing, project cost
estimates, and defining the properties within the SSA. He explained that these
materials were going to be shared with Oxford property owners on December
18, 2019 at City Hall at an evening meeting that every Oxford property owner
was invited to attend via a mailed notice.
Assistant to the City Manager Mike Strong reviewed a presentation with the
Committee on the topic. He explained what a SSA is and outlined the SSA
process. Mr. Strong reviewed the potential Oxford storm sewer SSA project
location and scope. He explained that a total of 16 parcels could potentially be
included in the SSA. He explained that in addition to the storm sewer installation,
the project would also include some curb and gutter installation, and the
resurfacing of the private Oxford Road drive. Mr. Strong reviewed a potential
project schedule if the property owners successfully petition their follow
neighbors to initiate an SSA. He explained that in order for the City to move
forward with the SSA, the property owners defined within the SSA area would
need to submit a petition that demonstrates 2/3 property owner consent. He
explained that at this time, staff had very high level, per parcel, SSA project cost
estimates and that more accurate costs could not be developed until after
2
preliminary design is complete. He explained that if the property owners submit a
successful 2/3 petition to the City, the City would pay the upfront cost for the
design. He explained that the money would then be recaptured by the City if
the SSA is officially established in the future.
The Committee and City staff had discussions about how the City funds SSA
projects and the potential cost to Oxford property owners.
Kenneth Moan, Lake Forest resident of 2 Oxford Road, explained that Oxford
Road has an informal HOA group to manage their private drive. He explained
that this type of project is something above the group’s experience level in
managing. He explained that he is looking forward to the next step of meeting
with the majority of his neighbors at the public informational meeting held by the
City next week.
The Committee, City staff and the residents in attendance had discussions about
the project process, timeline, defining the properties that would be considered
as part of the SSA, and the potential benefits.
The Committee thanked the residents in attendance for attending tonight’s
meeting and encouraged them to encourage their neighbors to attend next
week’s public information meeting at City Hall.
II. REVIEW OF WINTER 2019/2020 SNOW PLAN – MICHAEL THOMAS & DAN MARTIN
Director Thomas explained that the Snow Plan has existed for approximately 15
years. He explained that the plan is reviewed and updated on annual basis. He
explained that the plan covers every detail of the City’s entire snow operations.
Director Thomas reviewed the plan priorities and highlighted that every snow
event is different and can cause the timing associated with when the priorities to
potentially change on an event-by-event basis.
The Committee and City staff discussed the snow event employee scheduling
and call in process, sidewalk snow removal contractual services, and the data
staff records throughout the snow season that tracks total costs.
The Committee and City staff discussed the IDOT Route 60 & 43 snow removal
agreement, the liability associated with the agreement, intersection clearing
responsibilities, communicating the City’s new responsibilities with neighboring
communities, evaluating the overall effectiveness of the agreement after the
snow season, the agreement’s impact on City street snow removal services, and
receiving and processing payment from IDOT. Director Thomas explained that
the City’s new responsibility had been identified and outlined in the 2019/2020
Snow Plan. City Manager Jason Wicha explained that once the agreement is
officially executed the news will be shared with the residents of Lake Forest as
well as neighboring communities.
The Committee and City staff discussed the City’s snowbird program and the
plowing of City sidewalks.
3
The Committee wished staff best of luck with the upcoming snow season.
III. UPDATE REGARDING PROPOSED IDOT JURISDICTIONAL TRANSFER FOR THE
DEERPATH & RTE. 41 PUMP STATION PROJECT – MICHAEL THOMAS
Director Thomas explained that easement request agreements from IDOT have
been submitted to ComEd and UP. He explained that both utilities have
expressed their support in granting the necessary easements.
Director Thomas explained that the questions in regards to IDOT’s rights to
construct the pump station on the property and then transfer it to the City that
were previously reviewed by the Committee were submitted to IDOT from the
City Attorney’s Office. He explained that the questions have been directed to
IDOT’s main attorney’s office in Springfield for their review and response. He
explained that following the response City staff and IDOT will need to meet to
discuss the project schedule.
The Committee and City staff discussed the questions proposed by the City
Attorney’s Office and potential next steps IDOT may need to take.
The Committee and City staff discussed the Everett and Route 43 Project.
Superintendent Ells explained that Metra was still looking to schedule a meeting
with the State and the City to discuss submitting a grant proposal for the required
track crossing upgrades.
ACTION ITEMS
IV. APPROVAL OF THE OCTOBER 30, 2019 PUBLIC WORKS COMMITTEE MEETING
MINUTES
Alderman Rummel to approve the October 30, 2019 Public Works Committee
meeting minutes. Alderman Moreno seconded the motion, which carried
unanimously.
V. REVIEW AND RECOMMEND APPROVAL TO CITY COUNCIL A CODE UPDATE
REGARDING SUMP PUMP & DOWNSPOUT DISCHARGE AS IT RELATES TO PROPERTY
LINES AND PUBLIC RIGHT-OF-WAY – CATHY CZERNIAK
Director Czerniak explained that the proposed code amendment is minor in
scope, however, it is still important. Director Czerniak explained that as the City
continues to experience heavy rainfall events, staff has become increasingly
more aware of situations where residents have installed private systems that
discharge at or near property lines. She explained that the goal of these systems
is to move stormwater of a private property as quickly as possible, however,
these discharge points can negatively impact an adjacent property owner,
sidewalk, parkway, or street. In many cases if the discharge point was just set
back more centrally on the property creating the discharge, many of these
issues could be avoided. Director Czerniak explained that currently, the City
code does not speak to where privately installed pipes are allowed to discharge.
When an issue arises at a private property, City staff encourages the property
4
owner to move any issue causing discharge points away from any issue area,
however, there is nothing in City Code that requires a property owner to do so.
She explained these issues were the impetus to recommend the code change.
She explained that in reviewing this particular section of the code there were
other recommended changes that were identified and recommended.
Director Czerniak reviewed the recommended code changes. She explained
that rather than requiring a property to connect private sump pump and storm
sewer systems to a public storm sewer, the connection requirement would be at
the discretion of the City Engineer and not mandatory. She explained that in
some cases it might be a better option to have these systems daylight onto the
private owner’s property than the City’s storm sewer system. She explained that
having systems that daylight decreases the capacity burden on the City storm
system and also provides additional environmental benefits by allowing the
stormwater to infiltrate soil naturally. She explained that some general updates to
the type of material that should be used for storm sewer pipes was also updated
to be more consistent with current construction and engineering standards. She
explained that revisions were also recommended to limit connections being
made to City road drains. She explained that road drains are not adequate to
support direct connections from private systems. The recommended language
only allows approved connections to road drain if the City Engineer determines it
is appropriate following their review. Lastly, the code update would also establish
a minimum distance from property lines for discharge points to resolve the issue
and the overall impetus for the recommended updates.
The Committee and City staff had discussions about non-residential properties
and stormwater detention.
Chairman Buschmann recommended one minor language change to the
proposed updated language. Director Czerniak explained that she would
incorporate the suggested edit.
Alderman Moreno moved to recommend approval to City Council a Code
update regarding sump pump & downspout discharge as it relates to property
lines and public right-of-way. Alderman Rummel seconded the motion, which
carried unanimously.
VI. REVIEW AND RECOMMEND APPROVAL TO CITY COUNCIL FINAL DRAFT OF THE
INFLOW & INFILTRATION POLICY – JIMMY LOCKEFEER
Management Analyst Jim Lockefeer explained that following the October 30,
2019 Committee meeting and at the direction of the Committee, staff shared
the latest version of the draft policy at the November 12, 2019 Finance
Committee meeting. He explained that at the Finance Committee meeting, the
Committee shared comments supporting a policy that focused more on
5
education and less on enforcement and fining non-complaint private property
owners who do not make the necessary repairs.
He explained that following the Finance Committee meeting, staff updated the
policy to reflect the comments shared at the meeting. He explained that that
there were no new additions to the policy, however, the “Private Property I&I
Procedures” section was scaled back. He explained that language on
enforcement and fining non-complaint homeowners was removed from the
section. He explained that homeowners would still receive mailed notice from
the City alerting them of any private identified I&I issues. He explained that the
letter will highlight why correcting I&I issues are important and recommend that
the homeowner contact the City to coordinate a meeting to discuss the
identified issues in person. Mr. Lockefeer explained that the policy still does not
replace the City’s Home Inspection Program which requires any identified
prohibited connections from the property to the City’s sanitary sewer system be
corrected prior to any change in ownership.
The Committee and City staff had discussions about the necessary repairs to
correct public I&I issues and future smoke testing.
Alderman Moreno moved to recommend approval to City Council of the final
draft of the Inflow & Infiltration Policy. Alderman Rummel seconded the motion,
which carried unanimously.
VII. REVIEW AND APPROVAL OF PUBLIC WORKS’ CORE & ELECTIVE DOCUMENT
MICHAEL THOMAS
Director Thomas explained that the reviews of every City Department’s Core and
Elective documents are part of the annual budget process. He explained that
last year, the Committee reviewed the Public Work’s document and made some
minor edits. He asked the Committee if there were any changes that they would
like to see made this year. There was consensus amongst the Committee that
there were no recommended changes that needed to be made.
The Committee and City staff had discussions about the gas light LED conversion
project.
Alderman Moreno moved to recommend approval of the Public Works’ Core &
Elective Document. Alderman Rummel seconded the motion, which carried
unanimously.
VIII. REVIEW AND RECOMMEND APPROVAL TO CITY COUNCIL THE PROPOSED FY ’21
CAPITAL EQUIPMENT – MICHAEL THOMAS
Director Thomas reviewed the proposed FY2021 Capital Equipment List. He
reviewed each piece of equipment being replaced by funding source.
Equipment being proposed for replacement was further outlined by department,
6
equipment details, and budget costs. Director Thomas reviewed detailed
replacement forms for each piece of equipment being requested.
The Committee and City staff had discussions about each requested piece of
equipment and how the equipment is utilized.
The Committee and City staff had discussions about the amount of ambulances
within the City’s fleet.
The Committee and City staff had discussions about how equipment and
vehicles can be repurposed and utilized by other departments.
The Committee and City staff discussed the City’s Fleet Section. Director Thomas
explained that the Fleet Section is doing extremely well and is fully staffed.
Director Thomas discussed the timing associated with bringing the topic to City
Council and ordering the equipment if the Committee recommends approval to
City Council. He reviewed the joint bid organizations and processes the
equipment is bid through in order to competitively purchase the equipment.
Alderman Rummel motioned to recommend approval to City Council the FY21
proposed capital equipment. Alderman Moreno seconded the motion, which
carried unanimously.
PUBLIC COMMENT
There was no additional public comment.
NEXT MEETING – TBD
The Committee agreed to leave the next date as to be determined.
Alderman Rummel explained that she attended a League of Women Voter
SWALCO presentation. She explained comments that were shared by the
SWALCO representative at the meeting.
ADJOURNMENT
Alderman Moreno moved to adjourn the meeting of the Public Works
Committee at 9:17 P.M. Alderman Rummel seconded the motion, which carried
unanimously.
Respectfully submitted,
Jim Lockefeer Jr.
Management Analyst
ACTION ITEM:
REVIEW AND RECOMMEND
APPROVAL TO CITY COUNCIL THE
WATER PLANT GENERATOR RADIATOR
REPAIR BID
WATER PLANT
GENERATOR RADIATOR
REPAIR BID
Public Works Committee –February 19, 2020
Bid Process
Public bid process with a mandatory onsite pre-bid meeting
Company Name Dollar Amount Bid Notes
Midwest Power Industry,Inc.$38,985.00 Qualified Low Bidder
Steiner $39,757.64 Disqualified
Lion Heart No Bid Concerned about bond requirements
Piper Electric No Bid Electrical Repairs Only
Altorfer Cat No Bid No Response
Recommendation & Project Budget
City staff recommends awarding the bid in the amount of $38,985.00 with a 10% or $3,898
contingency to Midwest Power Industry.
FY2020 Funding Source Amount
Budgeted
Amount
Requested
Including
Contingency
Budgeted?
Y/N
Contractual Services
501-6071-435.35-10 $88,600.00 $35,000.00 Y
Contractual Services
501-6072-435.35-10 $129,652.00 $7,883.00 Y
Award of Bid in the Amount of $38,985.00 with a 10% or $3,898 Contingency to Midwest
Power Industry, Inc. for the Lake Forest Water Treatment Plant Emergency Generator
Radiator Rebuild.
STAFF CONTACT: Dan Martin, Superintendent of Public Works (847-810-3561)
PURPOSE AND ACTION REQUESTED: The Public Works Committee and staff request City
Council approval to award the bid to rebuild the radiator on the emergency generator
located at the Water Plant to Midwest Power Industry, Inc.
BACKGROUND/DISCUSSION: The Lake Forest Water Treatment Plant has two very large
backup generators referred to as the west and east generators that were both installed
in 2004. Each generator has the capacity to operate the Water Plant at 80% production
demand. Only at times of peak water production do both generators need to be used
to operate the Water Plant during a utility power loss. This past fall during a routine
inspection, a small coolant leak was discovered coming from the west generator. The
service contractor investigated and identified two areas leaking from the core of the
radiator which is approximately 9 feet tall by 7.5 feet wide. The radiator core is
comprised of rows of tubes and serpentine fins that work to transfer heat to the cooling
fan. Staff proposed two options in the RFP: repair the generator using a new radiator or
rebuild the existing radiator.
Based on the estimate for a new replacement radiator to be in excess of $100,000 with
over a 12 month build lead time, staff chose to have the radiator rebuilt. The process
includes removing the top and bottom tanks and the side panels from the center core.
The inside of the tanks are flushed, prepped with new gaskets and everything is
remounted to the new core. The reassembled radiator is pressure tested and repainted
before being delivered and reinstalled. The rebuilt radiator will have a one year
warranty
PROJECT REVIEW/RECOMMENDATIONS:
Reviewed Date Comments
Public Works Committee 2/19/2020 Reviewed and Approved
BUDGET/FISCAL IMPACT: The repair followed the public bid process. The invitation to bid
was advertised in the newspaper. Five contractors attended the November 13, 2019
Mandatory Pre-Bid Meeting and two contractors submitted bids. One bidder was
disqualified due to not following the bid instructions. Staff reached out to each
contractor that did not submit a bid to inquire as to their reason for not doing so. One
contractor stated their concern with the bonding requirements, another admitted they
thought that it was strictly an electrical job, and the last contractor did not reply to the
inquiry.
2
Has City staff obtained competitive pricing for proposed goods/services? Yes
On December 2, 2019, staff received the following bids to rebuild the west generator:
Company Name Dollar Amount Bid Notes
Midwest Power Industry,Inc. $38,985.00 Qualified Low Bidder
Steiner $39,757.64 Disqualified
Lion Heart No Bid Concerned about bond
requirements
Piper Electric No Bid Electrical Repairs Only
Altorfer Cat No Bid No Response
Upon review of the received bids, staff recommends proceeding with the low bid
received by Midwest Power. Midwest Power currently holds the City’s preventative
maintenance contract for all City generators as part of the Municipal Partnering
Initiative. They have conducted favorable work. Midwest Power has also performed
well, providing services for the Illinois Tollway, Mill Creek Water Reclamation District and
Lake County Public works. Last year they rebuilt a radiator for the Illinois Tollway that
was similar in scope to this project. Midwest Power rebuilds the radiators in their own
workshop.
The total project cost including contingency of $42,883 is $2,912 over budget in the
Water Plant operating budget’s contractual services account. The $2,912 overage will
be covered by savings in other operating budget line items.
Below is an estimated summary of Project budget:
FY2020 Funding Source Amount
Budgeted
Amount
Requested
Including
Contingency
Budgeted?
Y/N
Contractual Services
501-6071-435.35-10 $88,600.00 $36,273.00 Y
Contractual Services
501-6072-435.35-10 $129,652.00 $3,698.00 Y
COUNCIL ACTION: Award of Bid in the Amount of $38,985.00 with a 10% or $3,898
Contingency to Midwest Power Industry, Inc. for the Lake Forest Water Treatment Plant
Emergency Generator Radiator Rebuild.
ACTION ITEM:
REVIEW AND RECOMMEND
APPROVAL TO CITY COUNCIL
FIRE DEPARTMENT’S
LOCKER ROOM PROJECT BID
Public Works Committee –February 19, 2020
Presentation Outline
•Background
•Existing Plan
•Designed Floor Plan
•Bid Process
•Recommendation & Project Budget
•Questions
Background
Locker Room has not been renovated or seen any significant modifications since it 1969
Numerous current issues with the locker room…
•Does not meet ADA regulations
•Does not accommodate lockers for all staff
•Does not accommodate two of the Department’s female fire fighters
•Third female firefighter may be hired soon
Summer of 2017 –FGM Architects conducts a needs assessment
Summer of 2019 –FGM approved to develop the drawings, specifications and assist with bid administration
Existing Plan
Designed Floor Plan
Bid Process
Public bid process with a mandatory pre-bid meeting
January 31, 2020 –11 bids received
Company Name Dollar Amount Bid
Reef Contractors $342,100.00
Slaton Construction Inc.$352,072.80
Master Project Inc.$356,400.00
Camosy $359,820.00
Efriam Carlson & Sons $374,800.00
Rasch Construction $383,400.00
Walter Daniels Construction $384,464.00
Pacific Construction Services LLC.$407,590.00
MAG Construction $422,516.00
Northwest Contractors Inc.$440,000.00
Manusos General Contracting $444,000.00
Recommendation & Project Budget
City staff recommends award of contract in the amount of $342,100 with a 10% or $34,210 contingency to Reef
Contractors and $25,000 to FGM Architects for project management for the Fire Department Locker Room
Renovation.
Category
FY2020 Budget $375,000
Architect Design Fees $43,150 $331,850
Construction $342,100 ($10,250)
10% Contingency $34,210 ($34,210)
FGM Project Man.$25,000 ($25,000)
Totals $444,460 ($69,460)
FY2020 Funding Source Amount
Budgeted
Amount
Requested
Budgeted?
Y/N
Capital Improvement Fund
311-1503-467.67-10 $375,000 $401,310 Y
Questions?
Award of Contract in the Amount of $342,100 with a 10% or $34,210 Contingency to Reef
Contractors and $25,000 to FGM Architects for Project Management for the Fire
Department Locker Room Renovation.
STAFF CONTACT: Dan Martin, Superintendent of Public Works (810-3561)
PURPOSE AND ACTION REQUESTED: The Public Works Committee and staff are requesting
approval of a bid for the Fire Department Locker Room Renovation Project included in
the FY2020 Capital Improvement Budget.
BACKGROUND/DISCUSSION: The Fire Department’s locker room located at the Public
Safety Building, has not been renovated or seen any significant modifications since it
was constructed in 1969, exceeding its expected useful life by many years. The locker
room facilities do not meet ADA regulations. The locker room is not able to
accommodate lockers for all staff, requiring lockers to be placed within the
restroom areas or kept in other office/sleeping quarters. Adding to the urgency to
renovate the locker room is the hiring of two female firefighters, who are
currently using a converted bathroom off the apparatus bay floor as a temporary
solution. Also, based on recent firefighter testing, the Department is potentially hiring a
third female in the near future, making the temporary solution more insufficient.
Recognizing this renovation project needed to be expedited, in summer of 2017 staff
retained FGM Architects, Inc. of Oak Brook, Illinois (FGM) for a sum of $8,000 to conduct
a needs assessment study of the locker room, in order to prepare conceptual drawings
and renovation costs to address the issues. In July of 2019, the Public Works Committee
and City Council reviewed and approved a contract to hire FGM to develop the
drawings, specifications and assist with bid administration for $43,150. FGM used the
selected design concept to address all ADA issues, provide three separate unisex
restrooms with a shower, vanity, toilet, and changing area for privacy. The plan also
expands the footprint to have all the lockers in one centralized location.
PROJECT REVIEW/RECOMMENDATIONS:
Reviewed Date Comments
Public Works Committee 2/19/20
Reviewed and Recommended City
Council Approval to Award
Construction and Project Management
City Council 8/5/2019 Approved FGM Architects Design
Services
Public Works Committee 7/23/19
Reviewed and Recommended City
Council Approval to Hire FGM
Architects for Design Services
Finance Committee 3/11/19 Discussion of Updated 5 Year CIP
Projects
BUDGET/FISCAL IMPACT: On January 31, 2020, staff received the following bids from
eleven contractors for the Fire Department Locker Room Renovation:
2
Has City staff obtained competitive pricing for proposed goods/services? Yes
Company Name Dollar Amount Bid
Reef Contractors $342,100.00
Slaton Construction Inc. $352,072.80
Master Project Inc. $356,400.00
Camosy $359,820.00
Efriam Carlson & Sons $374,800.00
Rasch Construction $383,400.00
Walter Daniels Construction $384,464.00
Pacific Construction Services LLC. $407,590.00
MAG Construction $422,516.00
Northwest Contractors Inc. $440,000.00
Manusos General Contracting $444,000.00
The renovation project followed the public bid process. The invitation was advertised in
the newspaper. The Mandatory Pre-Bid Meeting was well attended with eleven bids
being submitted at the January 31, 2020 public bid opening. After conducting a
complete review o the low bids by staff and FGM Architects, Reef Contractors bid
proposal met the project design specifications and is the low responsible bidder. Reef
Contractors provided favorable references from the following public entities:
Bolingbrook Park District, Chicago Housing Authority, Naperville Public Library, Harper
College, and Roselle Fire Station. The project Reef performed for Roselle Fire Station was
similar in scope to renovate their locker room. The Fire Chief had favorable comments
and overall was pleased with their performance.
The total project cost of $444,460 is $69,460 over the FY2020 amount of $375,000 as
broken down in the below chart.
Category
FY2020 Budget $375,000
Architect Design Fees $43,150 $331,850
Construction $342,100 ($10,250)
10% Contingency $34,210 ($34,210)
FGM Project Man. $25,000 ($25,000)
Totals $444,460 ($69,460)
As the economy continues to recover, project costs have been steadily rising and the
FY2020 amount of $375,000 in the five year CIP plan was not adjusted to reflect the
increases. Staff anticipates the $69,460 cost difference will be covered from remaining
funding from other building capital projects. Any remaining differences would need to
come from reserves.
If approved, City staff and the FGM will work with Reef Contractors to begin
construction in mid-April with substantial completion by the end of June.
3
Below is an estimated summary of Project budget:
FY2020 Funding Source Amount
Budgeted
Amount
Requested
Budgeted?
Y/N
Capital Improvement Fund
311-1503-467.67-10 $375,000 $401,310 Y
COUNCIL ACTION: Award of Contract in the Amount of $342,100 with a 10% or $34,210
Contingency to Reef Contractors and $25,000 to FGM Architects for Project
Management for the Fire Department Locker Room Renovation.